The following is copied from the Connecticut DOT website:
Why is Route 8 asphalt being removed? Visit our FAQ page here to find out.
Nighttime work will continue from 6PM to 6AM:
- Nighttime operations will typically occur Sunday night through Thursday night.
- Saw-cutting and concrete pavement repair activities will continue, northbound from Exit 15 to 22 (New Exits 12B to 18).
- Both northbound and southbound traffic lanes are moving to the right shoulder to create a work area for upcoming barrier replacement between Exit 20 and 22 (New Exits 17 – 18).
The week of Thanksgiving: work will cease Wednesday, November 27, and resume the following week, December 2.
There is no upcoming Daytime work.